谷歌宣布与可再生能源开发商Intersect Power和投资基金TPG Rise Climate合作,投资约200亿美元开发可再生能源、电池储能和电网升级,以满足其AI数据中心日益增长的电力需求。此举旨在应对AI数据中心电力短缺的预期,并加速可再生能源的部署。该项目将包括风能、太阳能和电池储能,预计首阶段将于2026年投入运营,2027年全面完工,这比核电项目更快。

🤝谷歌与Intersect Power和TPG Rise Climate达成协议,投资约200亿美元开发可再生能源,以满足其AI数据中心的电力需求。

⚡️该项目将包括风能、太阳能和电池储能,并将连接到与数据中心相同的电网点,谷歌将承担所需的电网升级费用。

🔋项目采用分阶段方法,第一阶段预计于2026年投入运营,2027年全面完工,这比核电项目的部署速度更快。

📈该交易还包括对Intersect Power的8亿美元股权投资,由TPG领投,谷歌等公司参与。

🌐美国目前有11,860个电力生产商连接电网的请求,总容量达2.05太瓦,几乎是当前已安装和连接容量的两倍,其中大部分是太阳能和电池项目。

Nuclear power may have received the lion’s share of attention from energy hungry tech companies over the past few months, with Google among them. But it appears that those new reactors won’t be enough for their AI ambitions: Google is now working with partners to build gigawatts of renewable power, battery storage, and grid upgrades to power its data centers.

Google announced Tuesday it signed a deal with renewable developer Intersect Power and investment fund TPG Rise Climate to spin up enough carbon-free power to drive several gigawatt-scale data centers. Altogether, the investment in renewable power will run about $20 billion, and Intersect is already financing the first project, the company told TechCrunch.

The deal also includes an $800 million equity investment in Intersect Power, with TPG leading the round and CAI, Google, and Greenbelt Capital Partners participating.

As tech companies like Google rush to bolster their AI capabilities, they’ve embarked on a building spree so vast that experts expect new AI data centers might be underpowered by 2027. That has forced tech companies to invest in new sources of energy.

For the new project, a hypothetical 1 gigawatt-scale data center would be matched with an equivalent amount each of wind, solar, and battery storage, which would have enough capacity to last two to four hours, Bloomberg reported. Both the data center and the renewable power park would be connected to the same point on the grid. Google  said it will foot the bill for any required upgrades to the grid. 

The hope is that the arrangement would help the data centers and renewable power parks get connected quickly. There are 11,860 active requests in the U.S. from power producers wanting to connect with the grid, according to Interconnection.fyi. A total of 2.05 terawatts of capacity are waiting, nearly double what’s currently installed and connected. The majority of those are for solar and battery projects.

Google and Intersect will be taking a phased approach, with the first phase operational by 2026 and fully completed by 2027, highlighting the speed at which renewable power can be deployed.

That pace should put pressure on nuclear power startups and developers, all of which have longer timelines. The quickest nuclear project — Microsoft’s restarting of a reactor at Three Mile Island — is scheduled to come online in 2028. Google’s deal with small modular reactor startup Kairos has a 2030 deadline for the first of several power plants, while Amazon’s contract with SMR startup X-Energy is targeting the early 2030s. 

All of that assumes the projects proceed as planned and are completed on time, something that has so far eluded the nuclear power industry.

Fish AI Reader

Fish AI Reader

AI辅助创作,多种专业模板,深度分析,高质量内容生成。从观点提取到深度思考,FishAI为您提供全方位的创作支持。新版本引入自定义参数,让您的创作更加个性化和精准。

FishAI

FishAI

鱼阅,AI 时代的下一个智能信息助手,助你摆脱信息焦虑

联系邮箱 441953276@qq.com

相关标签

谷歌 可再生能源 AI数据中心 能源投资 电网升级
相关文章